|
Meeting between
SHRA Representatives and Carillion plc
Wednesday 25th
September 2002, Offices of Sovereign Harbour Limited |
|
|
Representing
Carillion / SHL: |
|
|
Mark Orriss (MO)
|
Development
Director, Carillion |
|
|
Clifford Carvell
(CC) |
Project Director,
SHL |
|
|
Dan Hughes (DPH)
|
Marina Operations
Manager (Harbour Master) |
|
|
SHRA
Representatives: |
|
|
Reg Ludford (RL)
|
SHL Liaison |
|
|
Dave Hitchcock(DH) |
Planning Issues |
|
|
Clare Donovan
(CD) |
Chairman |
|
|
The second of
proposed regular meetings between the two groups to raise issues
important to those who live at the Harbour, this is a report of the
meeting and is not intended to represent accurate minutes.
Issues raised
stemmed from the last Public Meeting of the SHRA held on September 10th
as well as on-going issues from the previous meeting (June 14th). |
|
|
|
HEALTH CENTRE
As David May, from
Eastbourne PCT, had been seen leaving a meeting as we arrived,
discussions started with regard to the provision of a Health Centre at
the Harbour. |
|
|
RL |
asked if there was
a possibility that any proposed site would be donated by Carillion to
the SH Trust for the residents of the Harbour. |
|
|
MO |
said that
discussions were proceeding with the PCT. Government funds were
available, however, if assistance was to be provided this would most
likely take the form of a subsidy. The land would not be donated. SH
Trust will not be involved as this lies outside the remit of the Trust. |
|
|
A variety of
options were being discussed, with the PCT looking for a SHORT term as
well as a more permanent LONGER term solution. Carillion expect to need
a presence at the Harbour for at least another 2 years however this need
not necessarily be in their present offices. Help would be offered with
any suitable short term options if applicable. |
|
|
SEA DEFENCES |
|
|
RL |
asked for an
explanation for the delays to the proposed movement of shingle for sea
defences from October 1st to October 14th and questioned the provision
of a temporary road to the beach. |
|
|
MO |
With regard to the
road, there was a Planning issue relating to Planning consent given in
December 2001 remaining subject to a 106 agreement relating to buffer
zones at the roadside. Discussions were on-going with EBC. It is hoped
work will start on October 1st to provide access by a temporary road and
if this remains unavailable, access will be provided through Site N (Wimpey)
– with agreement from the Highways Authority - as an interim measure.
Carillion would not stand in the way of work starting when required. |
|
|
It was believed
that delays had been exacerbated by failure of the Environment Agency
and Pentium (responsible for the defence work) to agree a contract – now
understood to be resolved.
|
|
|
RL |
asked if SHL were
intending to write to all residents regarding movement of heavy lorries
as had been the policy in the past. |
|
|
CC |
This is the
responsibility of Pentium/ Environment Agency and help would be provided
by SHL if possible. |
|
|
MO |
Stressed that
lorry movements would be only short term and agreed that work should be
completed by December. |
|
|
PLAY AREAS
Some residents had
voiced disquiet at lack of play areas for their children. |
|
|
MO |
Each developer has
a responsibility to provide “open space” and EBC planning permission
requires this. SHL has no plans for any central amenities area.
However, SHL have made donations (amount specified and index linked) to
EBC for provision of “sports facilities”. It is the responsibility of
EBC to use these funds within 5 years of the second instalment (now
paid). |
|
|
DH |
suggested that a
letter be sent by SHRA to EBC to ascertain where and when these
facilities will be provided. (Paperwork specifies “within St Anthony’s
Ward”.) |
|
|
CC |
also confirmed
that Carillion are continuing to pay money to ESCC for continuing road
improvements, including cycleways. |
|
|
TRAFFIC CALMING
Again pleas had
been heard for traffic calming measures particularly along Atlantic and
Pacific Drives. There was discussion about which roads had been adopted
by EBC. |
|
|
CC |
ESCC (Highways)
had been asked to advise on requirements for Pacific Drive and the road
had been laid in accordance with agreed details, Any changes would need
to be agreed with the Highways Authority. |
|
|
MO |
a meeting was
scheduled with the above Authority and the subject would be raised (see
later notes). |
|
|
BUSES |
|
|
CC |
Eastbourne Bus Co
had not notified SHL of their intention to start the service to
Sovereign Harbour North. Enquiries will be made regarding insurance risk
as the roads have not yet been adopted by EBC. |
|
|
WEST HARBOUR
Easy access to
pontoons, particularly by children had been identified as a problem. |
|
|
DPH |
the problem had
been notified to Sunley Homes and they had now finished work to the
gates to prevent this problem recurring. |
|
|
RL |
drew attention to
a problem close to the Piazza – this will be investigated. |
|
|
CD |
queried plans to
provide gated access to pontoons adjacent to David Wilson site. |
|
|
DPH |
Future pontoon
usage may require a review of this matter. But there were currently no
plans to provide gates and therefore there should be no reason for David
Wilson to defer completion of the walkway. |
|
|
COVENANTS
The subject of
caravans/camper vans and commercial vehicles was raised. |
|
|
MO |
Land was sold to
developers with a restriction on caravans. The Builder is responsible
for upholding the covenants. This may defer to any management company
set up within developments following completion of the build programme
but could remain the responsibility of the builder even after site
completion. |
|
|
It was generally
agreed that this is a very difficult area and residents should discuss
matters between each other and take legal advice. |
|
|
CONTRACTORS
PARKING |
|
|
CC |
provided RL with
names and addresses of all developers so that letters could be sent
asking for control over contractor parking. |
|
|
SITE T (this is
the area linking North Harbour to the Waterfront)
It was confirmed
that walkway will be maintained during development of the site. The
bridge giving North Harbour residents access to the Waterfront will be
raised at times to match lock gates opening. |
|
|
MO |
Suggested there
may be times when access would be restricted for safety reasons
(Developer is Country Homes (currently Heritage Quay) under the name of
Grosvenor Quay). |
|
|
CD |
requested that a
notice be published when such times were known in advance to prevent
inconvenience to
North
Harbour residents. |
|
|
MO |
All large
residential sites had now been sold. |
|
|
CYCLEWAY
COMPLETION |
|
|
DH |
asked when there
was a planned completion of the cycleway between the Retail Park and
Atlantic Drive – there is a 5 feet stretch of pathway remaining
unfinished on the Carillion side of the fence. |
|
|
MO |
there are on-going
discussions with Prudential and EBC regarding this link with the retail
park and it remains a fundamental planning issue which also includes
continuation of the bus route from Atlantic Drive to ASDA. Carillion
would like it completed asap. The fencing around the retail park is the
property of Prudential and not Carillion.
There will be a
meeting with the Highways Authority this week to discuss matters
outstanding such as the pathway with Persimmon and WhiteOaks which
appear to be preventing completion of the walkways. |
|
|
MAINTENANCE
Questions had been
raised regarding defunct street lights and damaged bollards. |
|
|
MO |
will be dealt with
before Christmas |
|
|
DPH |
street lights have
bee numbered to ease identification of those not working. |
|
|
SH TRUST |
|
|
RL |
Voiced unease at
no local (resident) representation on the Trust in order to best protect
the interests of residents who pay money into the Trust. |
|
|
CD |
had the
Environment agency identified representatives for the Trust as discussed
at the last meeting? |
|
|
MO |
Nothing yet
forthcoming from the EA. The Constitution of the Trust was available
from the Trust’s solicitor and was readily available to all. (CD to
obtain a copy) |
|
|
HARBOUR CHARGES
Bill reminders had
been sent where necessary but numbers were not in excess of those
numbers normally expected. Invoices will be sent out in December and
following a review by the SHRA Committee, written explanation of how
charges are made will be sent out with each new invoice. |
|
|
DH |
apparently legal
challenges were being made to the charges as no capping is mentioned in
agreements. |
|
|
CC |
No legal
challenges had been received and the Divisor was likely to remain at
1500 for this year with an estimated charge being £100 – 120. |
|
|
MO |
hopes that the
current charges will be the highest likely. Charges are made on the
basis of necessary works in relation to budgets such that large
increases in charges should be planned for and spread across future
payments to prevent for “emergency” repairs etc. |
|
|
THE POND
It is anticipated
that material for infill will be provided from sites S and T. |
|
|
B&Q
The Public Enquiry
has been set for February 2003. It was hoped that the residents could
agree the benefits of the B&Q development in helping to allow for
completion of the Marina site as a whole. |
|
|
BOAT STORAGE
Boat storage will
not be possible in the future on sites S and T due to the proposed
development. Planning permission was being sought for this (temporarily)
on the proposed B&Q site. It was envisaged that boat movements would be
limited. [Boats need to have periods out of the water for
maintenance/repair] |
|
|
FUTURE PLANS
There are no
current plans for future, further Waterfront development and these will
not be subject to B&Q planning approval. |